Recap of how each of the school district buildings are being used and how many students attend each school as of December 2010. This information was supplied by the Communication Department of the District. The report shows
•There were 7,626 seats when all current school buildings are combined. As of December 31, 2010, total district enrollment
was 5,913. The district had 1713 empty seats.
•Both middle schools were at 65% of capacity.
•Capacity at the elementary school ranged from 58% to 98%.
•Based on recent enrollment numbers, total enrollment is declining.
Source: Kelley Munch – District Communications Department - January 2011 - Responses to questions emailed to the School Board.
Click on READ MORE below the attachment to view Q&A.
Update to the original Master Plan published in February 2006. The update is dated June 1, 2006.
Geneva District 304 Facilities Master Plan which was completed in 2006. This plan was the basis for the new elementary schools built in 2007 & 2009. The plan also called for an addition to the high school which did not go to referendum in 2009, though plans were completed.